Report: Moving disputed Falmouth turbine would cost $3M

FALMOUTH — One of the two wind turbines under a court order never to operate at their current spot may spin again on the wastewater treatment plant property, a little less than a half mile north from where it now stands. Accomplishing the move, however, would cost the town just over $3 million and isn’t likely to appease critics of the turbine’s current location. Weston and Sampson engineers were hired by selectmen to consider the possibility of relocating Wind II on the 329-acre

Source: Report: Moving disputed Falmouth turbine would cost $3M

Print Friendly, PDF & Email
Share

Iberdrola, EverPower, NextEra, Apex, Swift Energy…they are all talking to your Representatives…Are You?